CanaryMedia: “Is New England’s new hydropower transmission line paying off?” When the New England Clean Energy Connect [NECEC] transmission line started carrying electricity from Canada into Maine in January, supporters hailed the project as a triumph for renewable power. “Now, after nearly six months of operations, the early numbers raise questions about whether the project will be able to advance the region’s energy transition as much as advertised.” Energy flow into New England is up just marginally, and there have been roughly 27 days when no power at all traveled on the new line.
“If current trends hold, New England will receive less hydropower this year over two transmission lines than it did over just one line in 2023 and previous years.” Potentially putting further strain on the supply of Canadian hydropower is the Champlain Hudson Power Express, a transmission line that started sending electricity from Quebec into New York City this month.
In 2021, the transmission line through Maine was put on hold by a statewide referendum, until in 2023 a jury ruled the development could be restarted. “Two and a half years later, NECEC came online and started carrying the first electrons into New England.” It’s certainly a notable achievement in a time when the administration has been doing all it can to stop progress on clean energy, including offshore wind—the cornerstone of the Northeast’s decarbonization plans.
There were some early hiccups with the line, the longest with it being de-energized for nearly two weeks at the end of May and beginning of June. “With any new transmission infrastructure, a period of optimization and fine-tuning is to be expected.”
By my reckoning, the best optimization would be getting the current administration out of office lickety-split, so that we can put more electrons to work, and phase out molecules of hydrocarbons.
https://www.canarymedia.com/articles/transmission/new-england-hydropower-transmission-line